December 05 - Major Progress and Major Damage
 
That is: major progress to the boat, and major damage to our wallets.
 
 
Master stateroom bath:
 
  • Plumbing continues
  • Subfloor is complete.
  • The tub has been installed with granite top
  • Travertine installed on walls above tub
  • Ceiling panels ready for painting
  • Walls ready for veneers
  • Need to build medicine cabinet above vanity
  • Vanity ready for varnishing
  •  
    Granite vanity top complete
  •  
    Toilet support complete
  • All electrical wiring roughed in

 

Master stateroom:

 

  • Air handler installation in progress
  • Ceiling panels ready to be covered with majililte
  • All electircal wiring roughed in

 

Port guest stateroom bath:

 

  • Plumbing continues
  • Flooring is complete (except grouting)
  • Ceiling panels not started
  • Walls ready for veneers
  • Toilet ready for installation
  • All electrical wiring roughed in
  • Travertine installed on shower walls

 

Port guest stateroom:

 

  • Subfloor complete
  • Ceiling panels ready to be covered
  • Stereo cabinet ready for varnishing
  • All electrical wiring roughed in
  • Walls ready for veneers

 

Stbd guest stateroom:

 

  • All electrical wiring roughed in
  • Ceiling panels ready to be covered
 
Passageway:
 
  • New AC curcuit breaker panel ready for installation
  • Still need to reaplce/remove sump

 

Engine room:

 

  • Arg!
  • Removed / replaced cable trays
  • Removed all dead electrical cable (1000+ lbs)
  • Replacing DC electrical panel
  • Replacing 12V & 24V battery chargers
  • Replacing 100amp and 50 amp circuit breakers
  • Installing NMEA 2000 cable

 

Salon and Galley Windows:

 

  • Window frames (inside and out) in progress
  • Thermopane glass windows on order

 

Lazarette/Transom:

 

  • Glendinnings installed
  • Access doors on transom not started

 

Swim platform:

 

  • Sandblasted and painted
  • Waiting for magahony grid & ladder to be reinstalled

 

Exterior:

 

  • Bottom paint not started
  • Bottom repairs not started
  • Bow thruster ready for final assembly

 

Fresh water tank:

 

  • Sandblasting complete
  • Painting complete
  • New gaskets for inspection hatches
  • New SS pickup tube installed
  • Fluid level sensor still to be installed