December 05 - Major Progress and Major Damage
That is: major progress to the boat, and major damage to our wallets.
Master stateroom bath:
Plumbing continues
- Subfloor is complete.
The tub has been installed with granite top
Travertine installed on walls above tub
Ceiling panels ready for painting
Walls ready for veneers
Need to build medicine cabinet above vanity
Vanity ready for varnishing
Granite vanity top complete
Toilet support completeAll electrical wiring roughed in
Master stateroom:
Air handler installation in progress
Ceiling panels ready to be covered with majililte
All electircal wiring roughed in
Port guest stateroom bath:
Plumbing continues
Flooring is complete (except grouting)
Ceiling panels not started
Walls ready for veneers
Toilet ready for installation
All electrical wiring roughed in
Travertine installed on shower walls
Port guest stateroom:
Stbd guest stateroom:
All electrical wiring roughed in
Ceiling panels ready to be covered
Engine room:
Arg!
Removed / replaced cable trays
Removed all dead electrical cable (1000+ lbs)
Replacing DC electrical panel
Replacing 12V & 24V battery chargers
Replacing 100amp and 50 amp circuit breakers
Installing NMEA 2000 cable
Salon and Galley Windows:
Lazarette/Transom:
Swim platform:
Exterior:
Fresh water tank:
Sandblasting complete
Painting complete
New gaskets for inspection hatches
New SS pickup tube installed
Fluid level sensor still to be installed